Contract summary

Get Adobe Reader View a detailed summary of the contract (PDF, 3mb)

For a shorter summary, click on the links below to go to the relevant section.

The contractor The project The contract Term of contract
Related parties Payments Availability and reliability adjustments Tolls
Asset transfers Risk transfer Additional trains Millennium trains
Guarantees      

The contractor

Reliance Rail Pty Limited
Suite 2, Level 9
333 George St
Sydney NSW 2000
www.reliancerail.com.au

Equity investors in Reliance Rail:

The project

The finance, design, manufacture and through life support of:

This is for the purpose of making up to 72 trains available to RailCorp for timetabled service each day until the end of the contract term.

The contractor may provide additional associated services such as vandalism repair and downloading of CCTV images.

The contract

The contract is a suite of agreements rather than a single document.

Get Adobe Reader View a diagram of the contractual matrix (PDF, 327kb)

All the contracts to which RailCorp is a party are published on this website. See Schedule of agreements.

Term of contract

The contract became effective on 7 December 2006.
The term continues for 30 years after the delivery of the tenth-last train (i.e. until about 2043) and may at RailCorp’s option be extended for two further periods each of five years.

Related parties

See Schedule of agreements.

Payments

The contractor is entitled to receive:

Availability and reliability adjustments

Availability payments are made subject to adjustments for each train which is, by default on the part of the contractor:

The adjustments are progressively increased to the steady state level during the 30 months from the introduction of the first train.

Extended poor performance may lead to termination of the contract.

Tolls

The contractor is not entitled to receive any public tolls, usage charges or any share in passenger fare revenue.

Asset transfers

RailCorp will provide a lease to the contractor of the maintenance facility at a nominal rent when construction is complete (forecast 2009). The site, including the maintenance facility to be built on it, reverts to RailCorp at the end of the term.

The trains remain the property of the contractor, who must dispose of them at the end of the contract. However, at its option, RailCorp may acquire some or all of the trains at the end of the contract at no cost.

The simulators become the property of RailCorp on the date of practical completion.

Risk transfer

The contractor takes financing risk, design risk, manufacturing risk, performance risk, and the risk of damage to the trains while at the maintenance facility.

RailCorp retains demand risk and the risk of damage being caused to the trains on the RailCorp network.

Additional trains

RailCorp may, at any time up to 18 months prior to the anticipated date of final completion of the last train, require the contractor to negotiate in good faith for the manufacture, through life support and financing of up to 20 additional trains and additional simulators.

Millennium trains

RailCorp may require the contractor to negotiate in good faith for the provision of maintenance and other through life support services at the maintenance facility in respect of the Millennium trains, which are presently maintained at Eveleigh by EDI Rail. (Downer-EDI Ltd, the parent company of EDI Rail, holds 49% of the equity in the contractor.)

Guarantees

The State of New South Wales provides a guarantee under the Public Authorities (Financial Arrangements) Act (NSW) of the obligations of RailCorp to:

 Rail Corporation New South Wales. PO Box K349 Haymarket NSW 1238 +61 (02) 8202 2000 (Switchboard).